A Quick Run will take all schedules that are active and run them all in order. For example:
Schedule A:
Z1 is set at 0.20"
Z2 is set at 0.05"
Z3 is set at 0.25"
Schedule B:
Z1 is set at 0.10"
Z2 is set at 0.05"
Z3 is set at 0.10"
Quick Run schedule will be:
Z1 is set at 0.20"
Z2 is set at 0.05"
Z3 is set at 0.25"
Z1 is set at 0.10"
Z2 is set at 0.05"
Z3 is set at 0.10"
If using Auto Water, it will result to doing 0.15" for each Zone. We recommend 0.15"-0.25" per watering event.
If you don't have schedules enabled, it will run three rotations for each zone, with Auto Water enabled or disabled.